Project Details
Comprises of Precast concrete Girder Beams with 38 Nos strands applied 7410kN pulling force and Solid Slabs
-
Client
M/s. Etihad Rail -
Services Provided
Design, production, delivery and erection -
Location
Al Ain –Abu Dhabi Road -
Completion Date
September 2021
Project Overview
The project had a 45-day erection timeline at the site. Tilt production involved 2,588 pieces (337.5 m² / 2,733.75 m³), including 270 girder beams (38 strands, 7,410 kN pulling force) and 2,318 solid slabs. Production commenced on March 8, 2021, with erection starting on March 20, 2021, and completed by September 29, 2021.