Etihad Rail Girder Beams

Project Details

Comprises of Precast concrete Girder Beams with 38 Nos strands applied 7410kN pulling force and Solid Slabs

  • Client
    M/s. Etihad Rail
  • Services Provided
    Design, production, delivery and erection
  • Location
    Al Ain –Abu Dhabi Road
  • Completion Date
    September 2021

Project Overview

Project Duration of 45 Days erection at site. The Tilt Production (2,588 Pcs/337.5 m2 / 2,733.75 m³ (Girder Beams 270 Nos with 38 Nos strands Applied 7410kN pulling force + Solid Slabs 2,318) commenced on 08-Mar-2021 and completed on 6th August 2021. Erection commenced on 20-Mar-2020 and completed by 29-Sep- 2021
Explore More
Related Projects

Decades of experience in design, production and erection of precast concrete elements for building projects across the GCC.

RELATED PROJECTS